In this article we explain under which Workflows you should raise a notice for the following contract types, so you have a quick reference guide:-
- NEC4 ECC - Quick Reference Clause Guide
- NEC4 ECS - Quick Reference Clause Guide
- NEC4 PSC - Quick Reference Clause Guide
- NEC4 TSC - Quick Reference Clause Guide
- NEC3 ECC - Quick Reference Clause Guide
- NEC3 ECS - Quick Reference Clause Guide
- NEC3 PSC - Quick Reference Clause Guide
You can also get a copy of the file as a spreadsheet if you need to set up a custom contract, although this article will be periodically updated with improvements, so the best thing to do is click the follow button.
NEC4 ECC - Quick Reference Clause Guide
NEC4 ECC |
|
Early Warning |
|
Project Manager Early Warning |
|
Increase the total of the Prices |
|
Delay Completion |
|
Delay meeting a Key Date |
|
Impair the performance of the works in use |
|
Adversely affect the creation or use of the Information Model |
|
Affect the achievement of another Partner's objectives |
|
Increase the Contractor's total cost |
|
Contractor Early Warning |
|
Increase the total of the Prices |
|
Delay Completion |
|
Delay meeting a Key Date |
|
Impair the performance of the works in use |
|
Adversely affect the creation or use of the Information Model |
|
Affect the achievement of another Partner's objectives |
|
Increase the Contractor's total cost |
|
Instructions |
|
Project Manager Instructions |
|
14.3 |
to change the Scope or a Key Date |
17.1 |
stating how to resolve an ambiguity or inconsistency |
17.2 |
to change the Scope to remove something which is illegal or impossible |
19.1 |
on how to deal with a prevention event |
23.1 |
to submit particulars of design of an item of Equipment |
24.2 |
to remove a person |
32.2 |
to submit a revised programme |
34.1 |
to stop or not start work or to start or restart work |
36.1 |
to submit a quotation for acceleration |
40.3 |
to correct a failure to comply with the quality plan |
60.6 |
to correct a mistake in the Bill of Quantities (main Options B and D) |
62.1 |
to submit alternative quotations for a compensation event |
73.1 |
on how to deal with an object of value of historical interest |
92.2 |
to leave Site, remove Equipment, Plant and Materials and assign the benefit of the subcontract to the Client |
X10.4 |
to submit a revised Information Execution Plan |
X12.1(6) |
providing Partnering Information |
X22.4 |
to remove a key person during Stage One |
X22.5 |
to remove work required in Stage Two from the Scope |
Other Instruction |
|
Programme |
|
PM Reply - Not Accepted |
|
The Contractor's plans which it shows are not practicable |
|
It does not show the information which the contract requires |
|
It does not represent the Contractor's plans realistically |
|
It does not comply with the Scope |
|
Notifications |
|
Project Manager Notifications |
|
13.2 |
of a change of address for communications |
13.5 |
of an agreement to extend the period for reply for a communication (excluding compensation events periods) |
14.2 |
of the cancellation of a delegation |
16.2 |
that the Client is considering a proposal |
17.1 |
of an ambiguity or inconsistency |
17.2 |
of an illegal or impossible requirement |
25.2 |
of an assessment of the amount to be paid as the Contractor failed to provide services |
25.3 |
of the amount assessed for a failure to meet a Key Date |
26.3 |
of an agreement that submission of subcontractor documents is not needed |
27.2 |
to provide access to the work being done and Plant and Materials being stored to those named |
28.1 |
on behalf of the Client of an intention to transfer the benefit of the contract |
30.2 |
of certification of the date of Completion |
35.3 |
of certification of the date of take over of part of the works |
41.6 |
of an assessment of the amount to be paid for repeating a test or inspection |
45.1 |
of a proposal to accept a Defect |
46.1 |
of the amount to be paid for uncorrected Defects |
46.2 |
of the cost the Contractor would incur in correcting a Defect |
50.9 |
of acceptance that part of the Defined Cost is correct (main Options C, D, E and F) |
50.9 |
of further records in respect of Defined Cost are needed (main Option C, D, E and F) |
50.9 |
of errors in the Contractor's assessment (main Option C, D, E and F) |
50.9 |
of the correct assessment of the part of the Defined Cost (main Option C, D, E and F) |
53.1 |
of certification of the final payment |
53.3 |
of the preliminary assessment of the Contractor's share (main Option C and D) |
53.4 |
of the final assessment of the Contractor's share (main Option C and D) |
61.5 |
that the Project Manager has decided the Contractor did not give early warning of a compensation event |
61.6 |
that an assumption on which a compensation event quotation is based was wrong |
86.1 |
of the insurance certificates for insurances taken out by the Client |
90.1 |
of a wish to terminate |
90.1 |
of the issue of a termination certificate |
91.2 |
of a default/of the Contractor having not put right a default |
91.3 |
of a default/of the Contractor having not put right a default |
92.2 |
that Equipment is no longer required |
W1.1(1) |
on behalf of the Client, the name of a replacement Senior Representative |
X7.3 |
of the amount of reduction in delay damages following take over of part of the works |
X18.6 |
of a matter for which the Contractor is liable |
X22.6(2) |
of the assessment to the change in the Budget |
Y2.3 |
of an intention to pay less than the notified sum |
Y3.3 |
on behalf of the Client of the name of the beneficiary |
Other notification |
|
Contractor Notifications |
|
13.2 |
of a change of address for communications |
17.1 |
of an ambiguity or inconsistency |
17.2 |
of an illegal or impossible requirement |
20.3 |
of advice on the practical implications of the design and subcontracting arrangements (main Options C, D, E and F) |
28.1 |
of an intention to transfer the benefit of the contract |
31.3 |
of a failure by the Project Manager to notify acceptance or non acceptance of a programme |
50.9 |
of when the Defined Cost of part of the works has been finalised (main Options C, D, E and F) |
61.4 |
of a failure by the Project Manager to respond to a compensation event notification |
62.6 |
of a failure by the Project Manager to respond to a quotation |
64.4 |
of a failure by the Project Manager to make an assessment of a compensation event |
73.1 |
that an object of value of of historical or other interest has been found |
90.1 |
of a wish to terminate |
W1.1(1) |
of the name of a replacement Senior Representative |
X10.4(2) |
of a failure by the Project Manager to notify acceptance or non acceptance of an Information Execution Plan |
Y2.3 |
of an intention to pay less than the notified sum |
Other notification |
|
Supervisor Notifications |
|
13.2 |
of change of address for communications |
14.2 |
of the cancellation of a delegation |
41.3 |
of a test or inspection or the result of a test or inspection |
42.2 |
that Plant and Materials have passed a test or inspection |
44.3 |
of the issue of the Defects Certificate |
Other notification |
|
Submissions |
|
Contractor Submissions |
|
16.1 |
a proposal to reduce the amount the Client pays to the Contractor |
16.3 |
a proposal to add an area to the Working Area |
20.4 |
forecasts of the total Defined Cost for the whole of the works (main Options C, D, E and F) |
21.2 |
particulars of design |
23.1 |
particulars of design for an item of Equipment |
24.1 |
details of a replacement person |
26.2 |
the name of a proposed subcontractor |
26.3 |
proposed subcontract documents |
26.4 |
pricing information in a proposed subcontract document (main Options C, D, E and F) |
40.2 |
a proposed quality policy statement or quality policy plan |
45.1 |
a proposal to accept a Defect |
50.9 |
records to demonstrate Defined Cost is correctly assessed (main Options C, D, E and F) |
55.3 |
a revised activity schedule (main Option A) |
84.1 |
certificates of insurance |
X4.1 |
an ultimate holding company guarantee |
X9.1 |
documents which transfer rights to the Client |
X10.4(1) |
an Information Execution Plan |
X10.4(3) |
a revised Information Execution Plan |
X13.1 |
a performance bond |
X14.2 |
an advance payment bond |
X15.1 |
a certificate of insurance |
X16.3 |
a retention bond |
X20.2 |
a report of performance |
X20.3 |
proposals for improving performance |
X21.1 |
a proposal to reduce the cost of operating and maintaining an asset |
X22.1(1) |
of a forecast of the total Defined Cost for the work in Stage One |
X22.3(1) |
a design proposal for Stage Two |
Y1.4 |
details of the banking arrangement for the Project Bank Account |
Y1.6 |
a proposal to add a Supplier to the Named Suppliers |
Y1.9 |
the Authorisation setting out sums due to the Named Suppliers |
Other submission |
|
Submission with quote |
|
36.1 |
a quotation for acceleration |
45.2 |
a quotation to accept a Defect |
X21.1 |
a quote to reduce the cost of operating and maintaining an asset |
Compensation Events |
|
60.1(1) | An instruction to change the Scope |
60.1(2) | Client does not provide access to the Site |
60.1(3) | Client does not provide something that it is to provide |
60.1(4) | An instruction to stop or not start work or to change a Key Date |
60.1(5) | Client or Others do not work within the stated constraints |
60.1(6) | Project Manager or Supervisor does not reply to a communication |
60.1(7) | An instruction dealing with an object of interest or value |
60.1(8) | Change of a decision |
60.1(9) | Withholds an acceptance |
60.1(10) | An instruction to search for a Defect and no Defect is found |
60.1(11) | A test or inspection causes unnecessary delay |
60.1(12) | Contractor encounters physical conditions |
60.1(13) | A weather measurement is recorded |
60.1(14) | An event which is the Client's liability |
60.1(15) | Project Manager certifies Take Over before Completion |
60.1(16) | Client does not provide material for testing |
60.1(17) | Notification of a correction |
60.1(18) | A breach by the Client |
60.1(19) | A prevention event |
60.1(20) | A notification that a quotation for a proposed instruction is not accepted |
60.1(21) | Additional compensation events stated in the Contract Data and identified below |
60.4 | A difference between the final total quantity of an item and the quantity in the Bill of Quantities which delays completion (main Options B and D) |
60.5 | A difference between the final total quantity of an item and the quantity in the Bill of Quantities (main Options B and D) |
60.6 | Correction of a mistake in the Bill of Quantities caused by a departure in the method of measurement |
X2.1 | A change in the law |
X12.3(7) | A change in the Partnering Information |
X14.2 | Delay in making advanced payment |
X15.2 | Correcting a Defect for which the Contractor is not liable |
Y2.5 | Suspension of performance |
NEC4 ECS - Quick Reference Clause Guide
NEC4 ECS | |
Early Warning | |
Contractor Early Warning | |
Increase the total of the Prices | |
Delay Completion | |
Delay meeting a Key Date | |
Impair the performance of the subcontract works in use | |
Adversely affect the creation or use of the Information Model | |
Affect the achievement of another Partner's objectives | |
Increase the subcontractor's total cost | |
Subcontractor Early Warning | |
Increase the total of the Prices | |
Delay Completion | |
Delay meeting a Key Date | |
Impair the performance of the subcontract works in use | |
Adversely affect the creation or use of the Information Model | |
Affect the achievement of another Partner's objectives | |
Increase the subcontractor's total cost | |
Instructions | |
Contractor Instructions | |
14.3 | to change the Subcontract Scope or a Key Date |
15.2 | to attend an early warning meeting between the Project Manager and the Contractor |
17.1 | stating how to resolve an ambiguity or inconsistency |
17.2 | to change the Subcontract Scope to remove something which is illegal or impossible |
19.1 | on how to deal with a prevention event |
23.1 | to submit particulars of design of an item of Equipment |
24.2 | to remove a person |
32.2 | to submit a revised programme |
34.1 | to stop or not start work or to start or restart work |
36.1 | to submit a quotation for acceleration |
40.3 | to correct a failure to comply with the quality plan |
60.6 | to correct a mistake in the Bill of Quantities (main Options B and D) |
62.1 | to submit alternative quotations for a compensation event |
73.1 | on how to deal with an object of value of historical interest |
92.2 | to leave Site, remove Equipment, Plant and Materials and assign the benefit of the subcontract to the Client |
X10.4 | to submit a revised Information Execution Plan |
X12.1(4) | providing Partnering Information |
Other Instruction | |
Programme | |
Contractor Reply - Not Accepted | |
The subcontractor's plans which it shows are not practicable | |
It does not show the information which the subcontract requires | |
It does not represent the subcontractor's plans realistically | |
It does not comply with the Subcontract Scope | |
Notifications | |
Contractor Notifications | |
13.2 | of a change of address for communications |
13.5 | of an agreement to extend the period for reply for a communication (excluding compensation events periods) |
14.2 | of the cancellation of a delegation |
16.2 | that the Contractor or Client is considering a proposal |
17.1 | of an ambiguity or inconsistency |
17.2 | of an illegal or impossible requirement |
25.2 | of an assessment of the amount to be paid as the subcontractor failed to provide services |
25.3 | of the amount assessed for a failure to meet a Key Date |
26.3 | of an agreement that submission of subcontractor documents is not needed |
27.2 | to provide access to the work being done and Plant and Materials being stored to those named |
28.1 | of an intention to transfer the benefit of the subcontract |
30.2 | of certification of the date of Completion |
35.3 | of certification of the date of take over of part of the subcontract works |
41.6 | of an assessment of the amount to be paid for repeating a test or inspection |
41.3 | of a test or inspection or the result of a test or inspection |
42.1 | that Plant and Materials have passed a test or inspection |
44.3 | of the issue of the Defects Certificate |
45.1 | of a proposal to accept a Defect |
46.1 | of the amount to be paid for uncorrected Defects |
46.2 | of the cost the subcontractor would incur in correcting a Defect |
50.9 | of acceptance that part of the Defined Cost is correct (main Options C, D, E and F) |
50.9 | of further records in respect of Defined Cost are needed (main Option C, D, E and F) |
50.9 | of errors in the subcontractor's assessment (main Option C, D, E and F) |
50.9 | of the correct assessment of the part of the Defined Cost (main Option C, D, E and F) |
53.1 | of certification of the final payment |
54.3 | of the preliminary assessment of the subcontractor's share (main Option C and D) |
54.4 | of the final assessment of the subcontractor's share (main Option C and D) |
61.5 | that the Contractor has decided the subcontractor did not give early warning of a compensation event |
86.1 | of the insurance certificates for insurances taken out by the Contractor |
90.1 | of a wish to terminate |
90.1 | of the issue of a termination certificate |
91.2 | of a default/of the subcontractor having not put right a default |
91.3 | of a default/of the subcontractor having not put right a default |
92.2 | that Equipment is no longer required |
X18.6 | of a matter for which the subcontractor is liable |
Y1.5 | of sums due to the subcontractor and the Named Suppliers |
Y2.3 | of an intention to pay less than the notified sum |
Y3.3 | the name of the beneficiary |
Other notification | |
Subcontractor's Notifications | |
13.2 | of a change of address for communications |
17.1 | of an ambiguity or inconsistency |
17.2 | of an illegal or impossible requirement |
20.2 | of advice on the practical implications of the design and subcontracting arrangements (main Options C, D, E and F) |
28.1 | of an intention to transfer the benefit of the contract |
31.3 | of a failure by the Contractor to notify acceptance or non acceptance of a programme |
50.9 | of when the Defined Cost of part of the works has been finalised (main Options C, D, E and F) |
61.4 | of a failure by the Contractor to respond to a compensation event notification |
62.6 | of a failure by the Contractor to respond to a quotation |
64.4 | of a failure by the Contractor to make an assessment of a compensation event |
73.1 | that an object of value of of historical or other interest has been found |
90.1 | of a wish to terminate |
X10.4(2) | of a failure by the Contractor to notify acceptance or non acceptance of an Information Execution Plan |
Y2.3 | of an intention to pay less than the notified sum |
Other notification | |
Submissions | |
Subcontractor Submissions | |
16.1 | a proposal to reduce the amount the Contractor pays to the subcontractor |
16.3 | a proposal to add an area to the Working Area |
20.3 | forecasts of the total Defined Cost for the whole of the subcontract works (main Options C, D, E and F) |
21.2 | particulars of design |
23.1 | particulars of design for an item of Equipment |
24.1 | details of a replacement person |
26.2 | the name of a proposed sub-subcontractor |
26.3 | proposed subcontract documents |
26.4 | pricing information in a proposed subcontract document (main Options C, D, E and F) |
40.2 | a proposed quality policy statement or quality policy plan |
45.1 | a proposal to accept a Defect |
50.9 | records to demonstrate Defined Cost is correctly assessed (main Options C, D, E and F) |
55.3 | a revised activity schedule (main Option A) |
84.1 | certificates of insurance |
X4.1 | an ultimate holding company guarantee |
X9.1 | documents which transfer rights to the Contractor |
X10.4(1) | an Information Execution Plan |
X10.4(3) | a revised Information Execution Plan |
X13.1 | a performance bond |
X14.2 | an advance payment bond |
X15.5 | a certificate of insurance |
X16.3 | a retention bond |
X20.2 | a report of performance |
X20.3 | proposals for improving performance |
X21.1 | a proposal to reduce the cost of operating and maintaining an asset |
Other submission | |
Submission with quote | |
36.1 | a quotation for acceleration |
45.2 | a quotation to accept a Defect |
Compensation Events | |
60.1(1) | An instruction to change the Subcontract Scope |
60.1(2) | Contractor does not provide access to the Site |
60.1(3) | Contractor does not provide something that it is to provide |
60.1(4) | An instruction to stop or not start work or to change a Key Date |
60.1(5) | Client, Contractor or Others do not work within the stated constraints |
60.1(6) | Contractor does not reply to a communication |
60.1(7) | An instruction dealing with an object of interest or value |
60.1(8) | Change of a decision |
60.1(9) | Withholds an acceptance |
60.1(10) | An instruction to search for a Defect and not Defect is found |
60.1(11) | A test or inspection causes unnecessary delay |
60.1(12) | Subcontractor encounters physical conditions |
60.1(13) | A weather measurement is recorded |
60.1(14) | An event which is the Client's or Contractor's liability |
60.1(15) | Contractor certifies Take Over before Completion |
60.1(16) | Contractor does not provide material for testing |
60.1(17) | Notification of a correction |
60.1(18) | A breach by the Contractor |
60.1(19) | A prevention event |
60.1(20) | A notification that a quotation for a proposed instruction is not accepted |
60.1(21) | Additional compensation events stated in the Subcontract Data and identified below |
60.4 | A difference between the final total quantity of an item and the quantity in the Bill of Quantities which delays completion (main Options B and D) |
60.5 | A difference between the final total quantity of an item and the quantity in the Bill of Quantities (main Options B and D) |
60.6 | Correction of a mistake in the Bill of Quantities caused by a departure in the method of measurement |
X2.1 | A change in the law |
X12.3(7) | A change in the Partnering Information |
X14.2 | Delay in making advanced payment |
X15.2 | Correcting a Defect for which the Subcontractor is not liable |
Y2.4 | Suspension of performance |
NEC4 PSC - Quick Reference Clause Guide
NEC4 PSC | |
Early Warning | |
Service Manager | |
Increase the total of the Prices | |
Delay Completion | |
Delay meeting a Key Date | |
Impair the usefulness of the services to the Client | |
Affect the work of the Client, a Client's Contractor or another consultant | |
Adversely affect the creation or use of the Information Model | |
Affect the achievement of another Partner's objectives | |
Increase the Consultant's total cost | |
Consultant Early Warning | |
Increase the total of the Prices | |
Delay Completion | |
Delay meeting a Key Date | |
Impair the usefulness of the services to the Client | |
Affect the work of the Client, a Client's contractor or another consultant | |
Adversely affect the creation or use of the Information Model | |
Affect the achievement of another Partner's objectives | |
Increase the Consultant's total cost | |
Instructions | |
Service Manager Instructions | |
14.3 | to change the Scope or a Key Date |
14.3 | to correct information provided by the Client |
16.1 | stating how to resolve an ambiguity or inconsistency |
16.2 | to change the Scope to remove something which is illegal or impossible |
18.1 | on how to deal with a prevention event |
21.2 | to remove a person |
32.2 | to submit a revised programme |
34.1 | to stop or not start work or to start or restart work |
35.1 | to submit a quotation for acceleration |
40.3 | to correct a failure to comply with the quality plan |
62.1 | to submit alternative quotations for a compensation event |
92.2 | to assign the benefit of any subcontractor to the Client |
X10.4 | to submit a revised Information Execution Plan |
X12.1(6) | providing Partnering Information |
Other Instruction | |
Programme | |
Reply - Not Accepted | |
The Consultant's plans which it shows are not practicable | |
It does not show the information which the contract requires | |
It does not represent the Consultant's plans realistically | |
It does not comply with the Scope | |
Notifications | |
Service Manager Notifications | |
13.2 | of a change of address for communications |
13.5 | of an agreement to extend the period for reply for a communication (excluding compensation events periods) |
14.2 | of the cancellation of a delegation |
16.1 | of an ambiguity or inconsistency |
16.2 | of an illegal or impossible requirement |
22.3 | of the amount assessed for a failure to meet a Key Date |
23.3 | of an agreement that submission of Subcontractor documents is not needed |
25.1 | on behalf of the Client of an intention to transfer the benefit of the contract |
30.2 | of certification of the date of Completion |
33.2 | on behalf of the Client of supply of information |
41.2 | of the amount to be paid for uncorrected Defects |
42.1 | of a proposal to accept a Defect |
50.9 | of acceptance that part of the Defined Cost is correct (main Options C and E) |
50.9 | of further records in respect of Defined Cost are needed (main Options C and E) |
50.9 | of errors in the subcontractor's assessment (main Options C and E) |
50.9 | of the correct assessment of the part of the Defined Cost (main Options C and E) |
53.1 | of certification of the final payment |
61.5 | that the Service Manager has decided the Contractor did not give early warning of a compensation event |
86.1 | of the insurance certificates for insurances taken out by the Client |
90.1 | of a wish to terminate |
90.1 | of the issue of a termination certificate |
91.2 | of a default/of the Consultant having not put right a default |
91.3 | of a default/of the Consultant having not put right a default |
X18.4 | of a matter for which the Consultant is liable |
Y2.3 | of an intention to pay less than the notified sum |
Y3.3 | on behalf of the Client of the name of the beneficiary |
Other notification | |
Consultant Notifications | |
13.2 | of a change of address for communications |
16.1 | of an ambiguity or inconsistency |
16.2 | of an illegal or impossible requirement |
22.2 | of a meeting with Others |
28.1 | of an intention to transfer the benefit of the contract |
31.3 | of a failure by the Service Manager to notify acceptance or non acceptance of a programme |
50.9 | of when the Defined Cost of part of the works has been finalised (main Options C and E) |
61.4 | of a failure by the Service Manager to respond to a compensation event notification |
62.6 | of a failure by the Service Manager to respond to a quotation |
64.4 | of a failure by the Service Manager to make an assessment of a compensation event |
90.1 | of a wish to terminate |
X10.4(2) | of a failure by the Service Manager to notify acceptance or non acceptance of an Information Execution Plan |
Y2.3 | of an intention to pay less than the notified sum |
Other notification | |
Submissions | |
Consultant Submissions | |
20.4 | forecasts of total expenses for the whole of the services (main Option A) |
20.5 | forecasts of total Defined Costs and expenses for the whole of the services (main Option C and E) |
21.1 | details of a replacement person |
23.2 | the name of a proposed subconsultant |
23.3 | proposed subcontract documents |
26.4 | pricing information in a proposed subcontract document (main Options C and E) |
40.2 | a proposed quality policy statement or quality policy plan |
42.1 | a proposal to accept a Defect |
50.9 | of records to demonstrate Defined Cost is correctly assessed (main Options C and E) |
51.1 | of an invoice |
53.1 | of an invoice in connection with the final payment |
55.3 | a revised activity schedule (main Option A) |
84.1 | certificates of insurance |
X4.1 | an ultimate holding company guarantee |
X9.1 | documents which transfer rights to the Client |
X10.4(1) | an Information Execution Plan |
X10.4(3) | a revised Information Execution Plan |
X13.1 | a performance bond |
X20.2 | a report of performance |
X20.3 | proposals for improving performance |
Y1.4 | details of the banking arrangement for the Project Bank Account |
Y1.6 | a proposal to add a Supplier to the Named Suppliers |
Y1.9 | the Authorisation setting out sums due to the Named Suppliers |
Other submission | |
Submission with quote | |
35.1 | a quotation for acceleration |
42.2 | a quotation to accept a Defect |
Compensation Events | |
60.1(1) | An instruction to change the Scope |
60.1(2) | Client does not provide access to a person, place or thing |
60.1(3) | Client does not provide something that it is to provide |
60.1(4) | An instruction to stop or not start work or to change a Key Date |
60.1(5) | Client or Others do not work within the stated constraints |
60.1(6) | Service Manager does not reply to a communication |
60.1(7) | Change of a decision |
60.1(8) | Withholds an acceptance |
60.1(9) | An event which is the Client's liability |
60.1(10) | Notification of a correction |
60.1(11) | A breach by the Client |
60.1(12) | A prevention event |
60.1(13) | Correcting a Defect for which the Consultant is not liable |
60.1(14) | An instruction correcting information provided by the Client |
60.1(15) | A notification that a quotation for a proposed instruction is not accepted |
60.1(16) | Additional compensation events stated in the Contract Data and identified below |
X2.1 | A change in the law |
X12.3(7) | A change in the Partnering Information |
Y2.5 | Suspension of performance |
NEC4 TSC - Quick Reference Clause Guide
NEC4 TSC | |
Early Warning | |
Service Manager Early Warning | |
Increase the total of the Prices | |
Interfere with the timing of the service | |
Impair the effectiveness of the service | |
Increase the Contractor's cost | |
Adversely affect the creation or use of the Information Model | |
Affect the achievement of another Partner's objectives | |
Contractor Early Warning | |
Increase the total of the Prices | |
Interfere with the timing of the service | |
Impair the effectiveness of the service | |
Increase the Contractor's total cost | |
Adversely affect the creation or use of the Information Model | |
Affect the achievement of another Partner's objectives | |
Instructions | |
Service Manager Instructions | |
14.3 | to change the Scope, a Task or the Affected Property |
14.5 | to correct a mistake in the Price List |
17.1 | stating how to resolve an ambiguity or inconsistency |
17.2 | to change the Scope to remove something which is illegal or impossible |
19.1 | to submit a quotation for a Task |
21.1 | to submit particulars of design of an item of Equipment |
22.2 | to remove a person |
32.2 | to submit a revised plan |
34.2 | to submit a revised Task Order programme |
36.1 | to stop or not start work or to start or restart work |
40.3 | to correct a failure to comply with the quality plan |
62.1 | to submit alternative quotations for a compensation event |
92.2 | to remove Equipment, Plant and Materials and assign the benefit of the subcontract to the Client |
X10.4(3) | to submit a revised Information Execution Plan |
X12.1(6) | providing Partnering Information |
Other Instruction | |
Notifications | |
Service Manager Notifications | |
13.2 | of a change of address for communications |
13.5 | of an agreement to extend the period for reply for a communication (excluding compensation events periods) |
14.2 | of the cancellation of a delegation |
16.2 | that the Client is considering a proposal |
17.1 | of an ambiguity or inconsistency |
17.2 | of an illegal or impossible requirement |
19.2 | of a quotation for a Task |
19.3 | of an extension to the period to submit a quotation or reply to a quotation |
23.2 | of an assessment of the amount to be paid as the Contractor failed to provide services |
24.3 | of an agreement that submission of Subcontractor documents is not needed |
25.2 | to provide access to the work being done and Plant and Materials being stored to those named |
26.1 | on behalf of the Client of an intention to transfer the benefit of the contract |
41.3 | of a test or inspection or the result of a test or inspection |
41.6 | of an assessment of the amount to be paid for repeating a test or inspection |
42.1 | that Plant and Materials have passed a test or inspection |
43.3 | of the amount to be paid for uncorrected Defects |
44.1 | of a proposal to accept a Defect |
44.2 | of the cost the Contractor would incur in correcting a Defect |
44.3 | of the issue of the Defects Certificate |
50.9 | of acceptance that part of the Defined Cost is correct (main Options C and E) |
50.9 | of further records in respect of Defined Cost are needed (main Options C and E) |
50.9 | of errors in the Contractor’s assessment (main Options C and E) |
50.9 | of the correct assessment of the part of the Defined Cost (main Options C and E) |
53.1 | of certification of the final payment |
54.3 | of the final assessment of the Contractor's share (main Option C) |
61.5 | that the Service Manager has decided the Contractor did not give early warning of a compensation event |
61.6 | that an assumption on which a compensation event quotation is based was wrong |
86.1 | of the insurance certificates for insurances taken out by the Client |
90.1 | of a wish to terminate |
90.1 | of the issue of a termination certificate |
91.2 | of a default/of the Contractor having not put right a default |
91.3 | of a default/of the Contractor having not put right a default |
92.2 | that Equipment is no longer required |
X18.6 | of a matter for which the Contractor is liable |
X19.1 | of a wish to terminate |
X19.1 | of the issue of a termination certificate |
X23.1 | extension of the Service Period |
X24.1 | assessment of final amount due in accounting period |
Y2.3 | of an intention to pay less than the notified sum |
Y3.3 | on behalf of the Client of the name of the beneficiary |
Other notification | |
Contractor Notifications | |
13.2 | of a change of address for communications |
17.1 | of an ambiguity or inconsistency |
17.2 | of an illegal or impossible requirement |
31.3 | of a failure by the Service Manager to notify acceptance or non acceptance of the plan |
33.3 | of a failure by the Service Manager to notify acceptance or non acceptance of the programme |
50.9 | of when the Defined Cost of part of the works had been finalised (main Options C and E) |
61.4 | of a failure by the Service Manager to respond to a compensation event notification |
62.6 | of a failure by the Service Manager to respond to a quotation |
64.3 | of a failure by the Service Manager to make an assessment of a compensation event |
90.1 | of a wish to terminate |
Y2.3 | of an intention to pay less than the notified sum |
Other notification | |
Submissions | |
Service Manager Submissions | |
86.1 | of certificates of insurance provided by the Client |
Submissions | |
Contractor Submissions | |
16.1 | a proposal to reduce the amount the Client pays to the Contractor |
16.3 | a proposal to add an area to the Service Area |
19.2 | of a quotation for a Task |
20.4 | forecasts of the total Defined Cost for the whole of the service (main Options C and E) |
21.1 | particulars of design for an item of Equipment |
22.1 | details of a replacement person |
24.2 | the name of a proposed Subcontractor |
24.3 | proposed subcontract documents |
26.4 | pricing information in a proposed subcontract document (main Options C and E) |
40.2 | a proposed quality policy statement or quality policy plan |
44.1 | a proposal to accept a Defect |
50.9 | records to demonstrate Defined Cost is correctly assessed (main Options C and E) |
55.3 | a revised Price List (main Option A) |
84.1 | certificates of insurance |
X4.1 | an ultimate holding company guarantee |
X10.4(1) | an Information Execution Plan |
X10.4(3) | a revised Information Execution Plan |
X13.1 | a performance bond |
X20.2 | a report of performance |
X20.3 | proposals for improving performance |
X21.1 | a proposal to reduce the cost of operating and maintaining an asset |
Y1.4 | details of the banking arrangement for the Project Bank Account |
Y1.6 | a proposal to add a Supplier to the Named Suppliers |
Y1.9 | the Authorisation setting out sums due to the Named Suppliers |
Other submission | |
Submission with quote | |
43.1 | a quotation to accept a Defect |
X21.2 | a quote to reduce the cost of operating and maintaining an asset |
Compensation Events | |
60.1(1) | An instruction to change the Scope, a Task or Affected Property |
60.1(2) | Client does not provide access to the Affected Property |
60.1(3) | Client does not provide something that it is to provide by agreed date |
60.1(4) | Task Order received after the starting date stated in the Task Order |
60.1(5) | An instruction to stop or not start work |
60.1(6) | Client or Others do not work within the stated constraints/conditions |
60.1(7) | Service Manager does not reply to a communication within timetable |
60.1(8) | Service Manager changes a decision previously communicated |
60.1(9) | Service Manager withholds acceptance |
60.1(10) | A test or inspection causes unnecessary delay |
60.1(11) | Change to the Affected Property |
60.1(12) | An event which is the Client's liability |
60.1(13) | Client does not provide material, facilities or samples for testing |
60.1(14) | Notification of a correction of assumption |
60.1(15) | A breach by the Client |
60.1(16) | Correct mistake in the Price List |
60.1(17) | A notification that a quotation for a proposed instruction/task is not accepted |
60.1(18) Additional compensation events stated in the Contract Data and identified below | |
X2.1 | A change in the law |
X10.5 | Alterations to Information Execution Plan |
X12.3(6) | A change in the Partnering Information |
X12.3(7) | A change in the Partnering timetable |
Y2.5 | Suspension of performance |
NEC3 ECC - Quick Reference Clause Guide
NEC3 ECC | |
Early Warning | |
Project Manager Early Warning | |
Increase the total of the Prices | |
Delay Completion | |
Delay meeting a Key Date | |
Impair the performance of the works in use | |
Affect the achievement of another Partner's objectives | |
Contractor Early Warning | |
Increase the total of the Prices | |
Delay Completion | |
Delay meeting a Key Date | |
Impair the performance of the works in use | |
Affect the achievement of another Partner's objectives | |
Increase the Contractor's total cost | |
Instructions | |
Project Manager Instructions | |
14.3 | to change the Works Information or a Key Date |
17.1 | to resolve an ambiguity or inconsistency |
18.1 | to change the Works Information to remove something which is illegal or impossible |
19.1 | on how to deal with a prevention event |
23.1 | to submit particulars of design of an item of Equipment |
24.2 | to remove an employee |
26.4 | to submit proposed contract data for a subcontract (main Options C, D, E and F) |
32.2 | to submit a revised programme |
34.1 | to stop or not start work or to start or restart work |
36.1 | to submit a quotation for acceleration |
44.2 | to change the Works Information after accepting a proposal not to correct a Defect |
62.1 | to submit alternative quotations for a compensation event |
73.1 | on how to deal with an object of value of historical interest |
82.1 | to not replace or repair the works, Plant and Material following loss or damage |
92.2 | to leave Site, remove Equipment, Plant and Materials and assign the benefit of the subcontract to the Employer |
X12.1(4) | providing Partnering Information |
Other Instruction | |
Programme | |
PM Reply - Not Accepted | |
The Contractor's plans which it shows are not practicable | |
It does not show the information which this contract requires | |
It does not represent the Contractor's plans realistically | |
It does not comply with the Works Information | |
Notifications | |
Project Manager Notifications | |
13.2 | of a change of address for communications |
13.5 | of an agreement to extend the period for reply for a communication (excluding compensation events periods) |
14.2 | of the cancellation of a delegation |
17.1 | of an ambiguity or inconsistency |
25.2 | of an assessment of the amount to be paid as the Contractor failed to provide services |
25.3 | of the amount assessed for a failure to meet a Key Date |
27.2 | to provide access to the work being done and Plant and Materials being stored |
30.2 | of certification of the date of Completion |
35.3 | of certification of the date of take over of part of the works |
40.6 | of an assessment of the amount to be paid for repeating a test or inspection |
44.1 | of a proposal to accept a Defect |
45.1 | of the amount to be paid for uncorrected Defects |
45.2 | of the cost the Contractor would incur in correcting a Defect |
53.3 | of the preliminary assessment of the Contractor's share (main Option C and D) |
53.4 | of the final assessment of the Contractor's share (main Option C and D) |
61.5 | that the Project Manager has decided the Contractor did not give early warning of a compensation event |
61.6 | that an assumption on which a compensation event quotation is based was wrong |
87.1 | of the insurance certificates for insurances taken out by the Employer |
90.1 | of a wish to terminate |
90.1 | of the issue of a termination certificate |
91.2 | of a default/of the Contractor having not put right a default |
91.3 | of a default/of the Contractor having not put right a default |
92.2 | that Equipment is no longer required |
X7.3 | of the amount of reduction in delay damages following take over of part of the works |
X18.5 | of a matter for which the Contractor is liable |
Y2.3 | of an intention to pay less than the notified sum |
Other notification | |
Contractor Notifications | |
13.2 | of a change of address for communications |
17.1 | of an ambiguity or inconsistency |
18.1 | of an illegal or impossible requirement |
20.3 | of advice on the practical implications of the design and subcontracting arrangements (main Options C, D, E and F) |
61.4 | of a failure by the Project Manager to respond to a Compensation Event notification |
62.6 | of a failure by the Project Manager to respond to a quotation |
64.4 | of a failure by the Project Manager to make an assessment of a Compensation Event |
73.1 | that an object of value of of historical or other interest has been found |
90.1 | of a wish to terminate |
Y2.3 | of an intention to pay less than the notified sum |
Other notification | |
Supervisor Notifications | |
13.2 | of change of address for communications |
14.2 | of the cancellation of a delegation |
40.3 | of a test or inspection or the result of a test or inspection |
41.1 | that Plant and Materials have passed a test or inspection |
43.3 | of the issue of the Defects Certificate |
Other notification | |
Submissions | |
Contractor Submissions | |
15.1 | a proposal to add an area to the Working Area |
20.4 | forecasts of the total Defined Cost for the whole of the works (main Options C, D, E and F) |
21.2 | particulars of design |
23.1 | particulars of design for an item of Equipment |
24.1 | details of a replacement person |
26.2 | the name of a proposed subcontractor |
26.3 | proposed subcontract documents |
26.4 | proposed contract data for each subcontract (main Options C, D E and F) |
44.1 | a proposal to accept a Defect |
54.2 | a revised activity schedule (main Option A and C) |
85.1 | certificates of insurance |
X4.1 | a parent company guarantee |
X13.1 | a performance bond |
X14.2 | an advance payment bond |
X20.2 | a report of performance |
X20.3 | proposals for improving performance |
Y1.4 | details of the banking arrangement for the Project Bank Account |
Y1.6 | a proposal to add a Supplier to the Named Suppliers |
Y1.9 | the Authorisation setting out sums due to the Named Suppliers |
Other submission | |
Submission with quote | |
36.1 | a quotation for acceleration |
44.2 | a quotation to accept a Defect |
Compensation Events | |
60.1(1) | An instruction to change the Works Information |
60.1(2) | Employer does not provide access to the Site |
60.1(3) | Employer does not provide something that he is to provide |
60.1(4) | An instruction to stop or not start work or to change a Key Date |
60.1(5) | Employer or Others do not work within the stated constraints |
60.1(6) | Project Manager or Supervisor does not reply to a communication |
60.1(7) | An instruction dealing with an object of interest or value |
60.1(8) | Change of a decision |
60.1(9) | Withholds an acceptance |
60.1(10) | An instruction to search for a Defect and no Defect is found |
60.1(11) | A test or inspection causes unnecessary delay |
60.1(12) | Contractor encounters physical conditions |
60.1(13) | A weather measurement is recorded |
60.1(14) | An event which is the Employer's risk |
60.1(15) | Project Manager certifies Take Over before Completion |
60.1(16) | Employer does not provide material for testing |
60.1(17) | Notification of a correction |
60.1(18) | A breach by the Employer |
60.1(19) | A prevention event |
60.4 | A difference between the final total quantity of an item and the quantity in the Bill of Quantities which delays completion (main Options B and D) |
60.5 | A difference between the final total quantity of an item and the quantity in the Bill of Quantities (main Options B and D) |
60.6 | Correction of a mistake in the Bill of Quantities caused by a departure in the method of measurement |
X2.1 | A change in the law |
X12.3(7) | A change in the Partnering Information |
X14.2 | Delay in making advanced payment |
X15.2 | Correcting a Defect for which the Contractor is not liable |
Y2.4 | Suspension of performance |
NEC3 ECS - Quick Reference Clause Guide
NEC3 ECS | |
Early Warning | |
Contractor Early Warning | |
Increase the total of the Prices | |
Delay Completion | |
Delay meeting a Key Date | |
Impair the performance of the works in use | |
Affect the achievement of another Partner's objectives | |
Subcontractor Early Warning | |
Increase the total of the Prices | |
Delay Completion | |
Delay meeting a Key Date | |
Impair the performance of the subcontract works in use | |
Affect the achievement of another Partner's objectives | |
Increase the Subcontractor's total cost | |
Instructions | |
Contractor Instructions | |
14.3 | to change the Subcontract Works Information or a Key Date |
17.1 | to resolve an ambiguity or inconsistency |
18.1 | to change the Subcontract Works Information to remove something which is illegal or impossible |
19.1 | on how to deal with a prevention event |
23.1 | to submit particulars of design of an item of Equipment |
24.2 | to remove an employee |
26.4 | to submit proposed contract data for a subcontract (main Options C, D, E and F) |
32.2 | to submit a revised programme |
34.1 | to stop or not start work or to start or restart work |
36.1 | to submit a quotation for acceleration |
44.2 | to change the Works Information after accepting a proposal not to correct a Defect |
62.1 | to submit alternative quotations for a compensation event |
73.1 | on how to deal with an object of value of historical interest |
82.1 | to not replace or repair the works, Plant and Material following loss or damage |
92.2 | to leave Site, remove Equipment, Plant and Materials and assign the benefit of the subcontract to the Employer |
X12.1(4) | providing Partnering Information |
Other Instruction | |
Programme | |
Contractor Reply - Not Accepted | |
The subcontractor's plans which it shows are not practicable | |
It does not show the information which this subcontract requires | |
It does not represent the subcontractor's plans realistically | |
It does not comply with the Subcontract Works Information | |
Notifications | |
Contractor Notifications | |
13.2 | of a change of address for communications |
13.5 | of an agreement to extend the period for reply for a communication (excluding compensation events periods) |
14.2 | of the cancellation of a delegation |
17.1 | of an ambiguity or inconsistency |
25.2 | of an assessment of the amount to be paid as the subcontractor failed to provide services |
25.3 | of the amount assessed for a failure to meet a Key Date |
27.2 | to provide access to the work being done and Plant and Materials being stored |
30.2 | of certification of the date of Completion |
35.3 | of certification of the date of take over of part of the works |
40.6 | of an assessment of the amount to be paid for repeating a test or inspection |
41.1 | that Plant and Materials have passed a test or inspection |
43.3 | of the issue of the Defects Certificate |
44.1 | of a proposal to accept a Defect |
45.1 | of the amount to be paid for uncorrected Defects |
45.2 | of the cost the subcontractor would incur in correcting a Defect |
53.3 | of the preliminary assessment of the subcontractor's share (main Option C and D) |
53.4 | of the final assessment of the subcontractor's share (main Option C and D) |
61.5 | that the Contractor has decided the subcontractor did not give early warning of a compensation event |
61.6 | that an assumption on which a compensation event quotation is based was wrong |
87.1 | of the insurance certificates for insurances taken out by the Employer |
90.1 | of a wish to terminate |
90.1 | of the issue of a termination certificate |
91.2 | of a default/of the Contractor having not put right a default |
91.3 | of a default/of the Contractor having not put right a default |
92.2 | that Equipment is no longer required |
X7.3 | of the amount of reduction in delay damages following take over of part of the works |
X18.5 | of a matter for which the subcontractor is liable |
Y1.5 | of sums due to the subcontractor and the Named Suppliers |
Y2.3 | of an intention to pay less than the notified sum |
Other notification | |
Subcontractor's Notifications | |
13.2 | of a change of address for communications |
17.1 | of an ambiguity or inconsistency |
18.1 | of an illegal or impossible requirement |
20.3 | of advice on the practical implications of the design and subcontracting arrangements (main Options C, D, E and F) |
61.4 | of a failure by the Contractor to respond to a compensation event notification |
62.6 | of a failure by the Contractor to respond to a quotation |
64.4 | of a failure by the Contractor to make an assessment of a compensation event |
90.1 | of a wish to terminate |
Y2.3 | of an intention to pay less than the notified sum |
Submissions | |
Subcontractor Submissions | |
15.1 | a proposal to add an area to the Working Area |
20.4 | forecasts of the total Defined Cost for the whole of the works (main Options C, D, E and F) |
21.2 | particulars of design |
23.1 | particulars of design for an item of Equipment |
24.1 | details of a replacement person |
26.2 | the name of a proposed subcontractor |
26.3 | proposed subcontract documents |
26.4 | proposed contract data for each subcontract (main Options C, D E and F) |
44.1 | a proposal to accept a Defect |
54.2 | a revised activity schedule (main Option A and C) |
85.1 | certificates of insurance |
X4.1 | a parent company guarantee |
X13.1 | a performance bond |
X14.2 | an advance payment bond |
X20.2 | a report of performance |
X20.3 | proposals for improving performance |
Y1.3 | a proposal to add a Supplier to the named list |
Other submission | |
Submission with quote | |
36.1 | a quotation for acceleration |
44.2 | a quotation to accept a Defect |
Compensation Events | |
60.1(1) | An instruction to change the Subcontract Works Information |
60.1(2) | Contractor does not provide access to the Site |
60.1(3) | Contractor does not provide something that he is to provide |
60.1(4) | An instruction to stop or not start work or to change a Key Date |
60.1(5) | Employer, Contractor or Others do not work within the stated constraints |
60.1(6) | Contractor does not reply to a communication |
60.1(7) | An instruction dealing with an object of interest or value |
60.1(8) | Change of a decision |
60.1(9) | Withholds an acceptance |
60.1(10) | An instruction to search for a Defect and no Defect is found |
60.1(11) | A test or inspection causes unnecessary delay |
60.1(12) | Subcontractor encounters physical conditions |
60.1(13) | A weather measurement is recorded |
60.1(14) | An event which is the Employer's or Contractor's risk |
60.1(15) | Contractor certifies Take Over before Completion |
60.1(16) | Contractor does not provide material for testing |
60.1(17) | Notification of a correction |
60.1(18) | A breach by the Contractor |
60.1(19) | A prevention event |
60.4 | A difference between the final total quantity of an item and the quantity in the Bill of Quantities which delays completion (main Options B and D) |
60.5 | A difference between the final total quantity of an item and the quantity in the Bill of Quantities (main Options B and D) |
60.6 | Correction of a mistake in the Bill of Quantities caused by a departure in the method of measurement |
X2.1 | A change in the law |
X12.3(7) | A change in the Partnering Information |
X14.2 | Delay in making advanced payment |
X15.2 | Correcting a Defect for which the Contractor is not liable |
Y2.4 | Suspension of performance |
NEC3 PSC - Quick Reference Clause Guide
NEC3 PSC | |
Early Warning | |
Employer Early Warnings | |
Increase the total of the Prices | |
Delay Completion | |
Change the Accepted Programme | |
Delay meeting a Key Date | |
Impair the usefulness of the services to the Employer | |
Affect the work of the Employer, an Employer's contractor or another consultant | |
Affect the achievement of another Partner's objectives | |
Consultant Early Warnings | |
Increase the total of the Prices | |
Delay Completion | |
Change the Accepted Programme | |
Delay meeting a Key Date | |
Impair the usefulness of the services to the Employer | |
Affect the work of the Employer, an Employer's Contractor or another Consultant | |
Affect the achievement of another Partner's objectives | |
Increase the Consultant's total cost | |
Employer Instructions | |
11.2(24) | to carry out a Task (main Option G) |
16.1 | to resolve an ambiguity or inconsistency |
17.1 | to change the Scope to remove something which is illegal or impossible |
18.1 | on how to deal with a prevention event |
20.2 | to change the Scope or a Key Date |
22.2 | to remove a person |
24.4 | to submit proposed contract data for a subcontract (main Options C and E) |
32.2 | to submit a revised programme |
33.1 | to stop or not start work or to start or restart work |
34.1 | to submit a quotation for acceleration |
40.3 | to correct a failure to comply with the quality plan |
62.1 | to submit alternative quotations for a compensation event |
Other Instruction | |
Programme | |
Employer Reply - Not Accepted | |
The Consultant's plans which it shows are not practicable | |
It does not show the information which this contract requires | |
It does not represent the Consultant's plans realistically | |
It does not comply with the Scope | |
Notifications | |
Employer Notifications | |
13.2 | of a change of address for communications |
13.5 | of an agreement to extend the period for reply for a communication (excluding compensation events periods) |
16.1 | of an ambiguity or inconsistency |
20.1 | of provision of information required by the contract |
23.3 | of the amount assessed for a failure to meet a Key Date |
30.2 | of certification of the date of Completion |
41.2 | of the amount to be paid for uncorrected Defects |
61.5 | that the Employer has decided the Contractor did not give early warning of a compensation event |
81.2 | of the insurance certificates for insurances taken out by the Employer |
90.1 | of having done one of the things at clause 90.1 |
90.3 | that the Employer no longer wants the services or the Consultant has substantially failed to comply with this contract |
90.4 | of termination due to a prevention event |
X10 | of the name of a replacement Employer's Agent |
X11 | of termination |
X18.3 | of a matter for which the Consultant is liable |
Y2.3 | of an intention to pay less than the notified sum |
Other notification | |
Consultant notifications | |
13.2 | of a change of address for communications |
16.1 | of an ambiguity or inconsistency |
17.1 | of an illegal or impossible requirement |
23.2 | of a meeting with Others |
41.1 | of Defects that have not been corrected at Completion |
61.4 | of a failure by the Employer to respond to a compensation event notification |
62.6 | of a failure by the Employer to respond to a quotation |
64.4 | of a failure by the Employer to make an assessment of a compensation event |
90.1 | of having done one of the things at clause 90.1 |
90.2 | of termination |
Other notification | |
Submissions | |
Consultant Submissions | |
21.3 | forecasts of total expenses for the whole of the services (main Option A) |
21.4 | forecasts of total Time Charge and expenses for the whole of the services (main Option C, E and G) |
22.1 | details of a replacement person |
24.2 | the name of a proposed Subconsultant |
24.3 | proposed subcontract documents |
24.4 | proposed contract data for each subcontract (main Options C and E) |
40.2 | a proposed quality policy statement or quality policy plan |
51.3 | further information to justify an invoice |
53.2 | a revised activity schedule (main Option A and C) |
71.1 | a request for permission to publicise the services |
81.2 | certificates of insurance |
91.2 | information resulting from work carried out to date |
X4.1 | a parent company guarantee |
X9.1 | documents which transfer rights to the Employer |
X13.1 | a performance bond |
X20.2 | a report of performance |
X20.3 | proposals for improving performance |
Other submission | |
Submission with quote | |
34.1 | a quotation for acceleration |
Compensation Events | |
60.1(1) | An instruction to change the Scope |
60.1(2) | Employer does not provide access to a person, place or thing |
60.1(3) | Employer does not provide something that he is to provide |
60.1(4) | An instruction to stop or not start work or to change a Key Date |
60.1(5) | Employer or Others do not work within the stated constraints |
60.1(6) | Employer does not reply to a communication |
60.1(7) | Change of a decision |
60.1(8) | Withholds an acceptance |
60.1(9) | Notification of a correction |
60.1(10) | A breach by the Employer |
60.1(11) | A prevention event |
60.1(12) | Correcting a Defect for which the Consultant is not liable |
60.1(13) | An instruction to change a Task Order (main Option G) |
60.1(14) | Consultant receives the Task Order after the starting date for the Task Order (main Option G) |
60.1(15) | A Task Completion is later than the Completion Date (main Option G) |
60.2 | A correction of a mistake in the Task Schedule |
X2.1 | A change in the law |
X12.3(7) | A change in the Partnering Information |
Y2.4 | Suspension of performance |