This article is a guide to using Aggregated Reports in FastDraft.
This guide contains the following:
- Getting started with the Aggregated Reporting Tool
- Data sets
- How to create new reports
- Scheduling Aggregate Reports
Related articles:-
- Using the Contract Dashboards and Registers
- Using RAG Notifications Panel
- Using Contract Health Check and Contract RAG Reports
- Using Third Party Reporting Tools
Getting started with the Aggregated Reporting Tool
The Aggregated reporting tool provides aggregated data sets for each workflow, across either all contracts if you have System Admin or Superuser permissions or all contracts each end user can access. It does not currently support aggregation of multiple workflows across all of your contracts, only each workflow individually. This can be done using macros in excel or by using third party reporting tool to aggregate data.
Data sets
The Aggregate reporting tool support the following data sets:
-
Actions -
- Actions - All
- Actions - Open
- Actions - Overdue
-
Certificates -
- Project Manager
- Contractor
- Client
- Supervisor
- Compensation Event
- Contract Other Price
- Contract Other Price Changes
- Contract Summary
- Contract User
- Defect
-
Delegated Actions -
- Project Manager
- Supervisor
- Supplier
- Document
- Early Warning
-
Extensions -
- Project Manager
- Supplier
- Forecast - Carbon
- Forecast - Cost
- Hub User
-
Instructions -
- Client to Project Manager
- Project Manager to Supplier
- Supervisor to Supplier
- Instruction to Search - Supervisor to Supplier
- Meeting
- Non-Conformance
- Non-Conformity
- Non-Conformity Proposal - Project Manager
-
Notifications -
- Client to Client
- Client to Project Manager
- Project Manager to Client
- Project Manager to Project Manager
- Project Manager to Supervisor
- Project Manager to Supplier
- Supervisor to Project Manager
- Supervisor to Supervisor
- Supervisor to Supplier
- Supplier to Supplier
- Supplier to Project Manager
- Other Assessments - Project Manager
- Payment Summary
- Payment Application - Supplier
- Payment Certificate - Project Manager
- Programme - Supplier
- Project List
- Project Order - Project Manager
- Proposal - Supplier
- Purchase Order Detail
- Quotation
- RFI/TQ - Supplier
- Site Diary
- System User
-
Submissions -
- Project Manager to Supplier
- Supplier to Project Manager
- Task Order - Project Manager
-
Test Inspection -
- Project Manager
- Supervisor
- Supplier
- Weather
Each dataset contains almost all of the data associated with an API endpoints or workflows allowing a very high degree of flexibility in third party tools like excel or Power BI. By way of example the following data fields are provided with the Early Warning data set for each early warning:
- URL Link to notice
- Form ID
- Project ID
- Contract ID
- Currency
- Company
- Project
- Contract
- Area
- Hub
- Framework
- Lot
- ID
- Subject
- Notification Date
- Notified By
- Reply Required
- Reply Received
- Reply Status
- Meeting Required
- Priority Action
- Action Owner
- Resolved
- Status
- Description
- Reply
- Reply By
- Reply Draft By
- Party
- Likelihood
- Severity
- Risk Types
- Relations
How to create new reports
Due to the potential size of the datasets for some queries, the tool doesn't display results on screen as this would slow down the end user machine unnecessarily. Instead our platform aggregates the dataset for you on our servers and saves a copy of the report to a Register. To start a new report request select the data set you want and time frame (optional) and click the Start Process action button. You can also select the Contract/Project Status you wish to see, though this is optional.
The Aggregate Reports List provides a historical audit list of all report run.
We are continually adding extra relevant information to the aggregate reports, e.g. Multi Currency support, and updates to allow for better analysis of data outside of FastDraft, i.e. Field IDs for Project, Contract and Form.
Updates to the platform can be accessed either via Reachback, or via New Features on the left hand side pane under smart links.
Scheduling Aggregate Reports
You can choose whether to run an aggregate report immediately or if you want to schedule a report to run on a regular basis. The options for scheduling aggregate reports are Daily, Weekly or Monthly, and you can select the day of the month you'd like to receive the report.
To schedule an aggregate report, within the aggregate reports page select the report type you'd like to schedule, and then select Schedule Report from the Run Mode dropdown. Continue to select the frequency and day of the week/month you'd like the report, then click Start Process.
At the bottom of the page is the Scheduled Reports section which shows you all reports that have been scheduled, as well as details such as when it last run and when the next report is due to run.
Once the report has run you will receive an email with a link to download the file.
To ensure scheduled reports remain active, they must be downloaded periodically. Reports that are not downloaded within the timeframes below will automatically stop running and be deleted:
- Daily reports: 7 days
- Weekly reports: 28 days
- Monthly reports: 3 months
Comments
0 comments
Please sign in to leave a comment.