This article is a guide to which clauses will trigger actions within FastDraft under different NEC4 contracts.
This guide contains the following:
Related Articles:
Introduction
For those using the new Action Reminders and To Do List (i.e. the action sidebar shows a tick instead of a bell), it's now also possible to configure certain communications to create a follow-up action based on the clause/type. For example, it's now possible to configure that a Project Manager's instruction to submit a programme creates an action on the Contractor to submit a programme a configured number of days later or to configure a reminder to resubmit when a programme is not accepted. Drop-down options can either be configured to always generate a follow-up action or to present a pop-up asking the user whether they would like to create a follow-up action. In either case, the resultant action is referred to as auto-generated. Auto-generated actions have a link to both the user and the communication that created them and can be edited/updated manually.
Our latest NEC4 master templates (v4.0 and above) have been updated to take advantage of this new capability as outlined below.
NEC4 ECC
Project Manager Instructions
Clause |
Action |
14.3 to change the Scope or a Key Date |
Prompt the PM to create a follow up action - PM Compensation Event |
17.2 to change the Scope to remove something which is illegal or impossible |
Prompt the PM to create a follow up action - PM Compensation Event |
23.1 to submit particulars of design of an item of Equipment |
Create a follow up action - Contractor Submission |
32.2 to submit a revised programme |
Create a follow up action - Contractor Submission |
34.1 to stop or not start work or to start or restart work |
Prompt the PM to create a follow up action - PM Compensation Event |
36.1 to submit a quotation for acceleration |
Create a follow up action - Contractor Submission with Quote |
73.1 on how to deal with an object of value of historical interest |
Prompt the PM to create a follow up action - PM Compensation Event |
X10.4 to submit a revised Information Execution Plan |
Create a follow up action - Contractor Submission |
X12.1(6) providing Partnering Information |
Create a follow up action - Contractor Submission |
Project Manager Notifications
Clause |
Action |
17.1 of an ambiguity or inconsistency |
Prompt the PM to create a follow up action - PM Instruction |
17.2 of an illegal or impossible requirement |
Create a follow up action - PM Instruction |
19.1 of a prevention event |
Create a follow up action - PM Instruction |
Contractor Notifications
Clause |
Action
|
17.1 of an ambiguity or inconsistency |
Prompt the Contractor to create a follow up action - PM Instruction |
17.2 of an illegal or impossible requirement |
Create a follow up action - PM Instruction |
19.1 of a prevention event |
Create a follow up action - PM Instruction |
73.1 that an object of value or of historical or other interest has been found |
Create a follow up action - PM Instruction |
NEC4 ECS
Contractor Instructions
Clause |
Action |
14.3 to change the Subcontract Scope or a Key Date |
Prompt the Contractor to create a follow up action - Contractor Compensation Event |
17.2 to change the Subcontract Scope to remove something which is illegal or impossible |
Prompt the Contractor to create a follow up action - Contractor Compensation Event |
23.1 to submit particulars of design of an item of Equipment |
Create a follow up action - Subcontractor Submission |
32.2 to submit a revised programme |
Create a follow up action - Subcontractor Submission |
34.1 to stop or not start work |
Prompt the Contractor to create a follow up action - Contractor Compensation Event |
36.1 to submit a quotation for acceleration |
Create a follow up action - Subcontractor Submission with Quote |
73.1 on how to deal with an object of value of historical interest |
Prompt the Contractor to create a follow up action - Contractor Compensation Event |
X10.4 to submit a revised Information Execution Plan |
Create a follow up action - Subcontractor Submission |
Contractor Notifications
Clause |
Action |
17.1 of an ambiguity or inconsistency |
Prompt the Contractor to create a follow up action - Contractor Instruction |
17.2 of an illegal or impossible requirement |
Prompt the Contractor to create a follow up action - Contractor Instruction |
Subcontractor Notifications
Clause |
Action |
17.1 of an ambiguity or inconsistency |
Create a follow up action - Contractor Instruction |
17.2 of an illegal or impossible requirement |
Create a follow up action - Contractor Instruction |
73.1 that an object of value of of historical or other interest has been found |
Create a follow up action - Contractor Instruction |
NEC4 ECSC
Client Instructions
Clause |
Action |
14.2 to change the Scope |
Prompt the Client to create a follow up action - Client Compensation Event |
30.4 to stop or not start work |
Prompt the Client to create a follow up action - Client Compensation Event |
70.1 on how to deal with an object of value or historical interest |
Prompt the Client to create a follow up action - Client Compensation Event |
NEC4 ECSS
Contractor Instructions
14.2 to change the Subcontract Scope |
Prompt the Contractor to create a follow up action - Contractor Compensation Event |
30.4 to stop or not start work |
Prompt the Contractor to create a follow up action - Contractor Compensation Event |
30.4 to remove work from the Scope |
Prompt the Contractor to create a follow up action - Contractor Compensation Event |
70.1 on how to deal with an object of value of historical interest |
Prompt the Contractor to create a follow up action - Contractor Compensation Event |
NEC4 FMC
Service Manager Instructions
Clause |
Action |
14.3 to change the Scope or the Affected Property |
Prompt the SM to create a follow up action - SM Compensation Event |
15.4 to change the scope following a decision at an early warning meeting |
Prompt the SM to create a follow up action - SM Compensation Event |
17.2 to change the Scope to remove something which is illegal or impossible |
Prompt the SM to create a follow up action - SM Compensation Event |
21.1 to submit particulars of design of an item of Equipment |
Create a follow up action - SP Submission |
32.2 to submit a revised plan |
Create a follow up action - SP Submission |
34.4 to submit a revised demobilisation plan |
Create a follow up action - SP Submission |
36.1 to stop or not start work |
Prompt the SM to create a follow up action - SM Compensation Event |
X10.4(3) to submit a revised Information Execution Plan |
Create a follow up action - SP Submission |
Service Manager Notifications
Clause |
Action |
17.1 of an ambiguity or inconsistency |
Create a follow up action - SM Instruction |
17.2 of an illegal or impossible requirement |
Create a follow up action - SM Instruction |
Service Provider Notifications
Clause |
Action |
17.1 of an ambiguity or inconsistency |
Create a follow up action - SM Instruction |
17.2 of an illegal or impossible requirement |
Create a follow up action - SM Instruction |
NEC4 FMS
Service Provider Instructions
Clause |
Action |
14.3 to change the Scope or the Affected Property |
Prompt the SP to create a follow up action - SP Compensation Event |
15.4 to change the scope following a decision at an early warning meeting |
Prompt the SP to create a follow up action - SP Compensation Event |
17.2 to change the Scope to remove something which is illegal or impossible |
Prompt the SP to create a follow up action - SP Compensation Event |
36.1 to stop or not start work |
Prompt the SP to create a follow up action - SP Compensation Event |
36.1 to remove work from the Scope |
Prompt the SP to create a follow up action - SP Compensation Event |
NEC4 PSC
Service Manager Instructions
Clause |
Action |
14.3 to change the Scope or a Key Date |
Prompt the SM to create a follow up action - SM Compensation Event |
16.2 to change the Scope to remove something which is illegal or impossible |
Prompt the SM to create a follow up action - SM Compensation Event |
32.2 to submit a revised programme |
Create a follow up action - Consultant Programme |
34.1 to stop or not start work |
Prompt the SM to create a follow up action - SM Compensation Event |
35.1 to submit a quotation for acceleration |
Create a follow up action - Consultant Submission with Quote |
X10.4 to submit a revised Information Execution Plan |
Create a follow up action - Consultant Submission |
Service Manager Notifications
Clause |
Action |
16.1 of an ambiguity or inconsistency |
Create a follow up action - SM Instruction |
16.2 of an illegal or impossible requirement |
Create a follow up action - SM Instruction |
Consultant Notifications
Clause |
Action |
16.1 of an ambiguity or inconsistency |
Create a follow up action - SM Instruction |
16.2 of an illegal or impossible requirement |
Create a follow up action - SM Instruction
|
NEC4 PSS
Contractor Instructions
Clause |
Action |
14.3 to change the Subcontract Scope or a Key Date |
Prompt the Contractor to create a follow up action - Contractor Compensation Event |
17.2 to change the Subcontract Scope to remove something which is illegal or impossible |
Prompt the Contractor to create a follow up action - Contractor Compensation Event |
32.2 to submit a revised programme |
Create a follow up action - Subcontractor Programme |
34.1 to stop or not start work or to start or restart work |
Prompt the Contractor to create a follow up action - Contractor Compensation Event |
35.1 to submit a quotation for acceleration |
Create a follow up action - Subcontractor Submission with Quote |
X10.4(3) to submit a revised Information Execution Plan |
Create a follow up action - Subcontractor Submission |
Contractor Notifications
Clause |
Action |
16.1 of an ambiguity or inconsistency |
Create a follow up action - Contractor Instruction |
17.2 of an illegal or impossible requirement |
Create a follow up action - Contractor Instruction |
Subcontractor Notifications
Clause |
Action |
16.1 of an ambiguity or inconsistency |
Create a follow up action - Contractor Instruction |
17.2 of an illegal or impossible requirement |
Create a follow up action - Contractor Instruction |
NEC4 PSSC
Client Instructions
Clause |
Action |
14.2 to change the Scope |
Prompt the Client to create a follow up action - Client Compensation Event |
30.4 to stop or not to start work |
Prompt the Client to create a follow up action - Client Compensation Event |
30.4 to remove work from the Scope |
Prompt the Client to create a follow up action - Client Compensation Event |
NEC4 TSC
Service Manager Instructions
Clause |
Action |
14.3 to change the Scope, a Task or the Affected Property |
Prompt the SM to create a follow up action - SM Compensation Event |
17.2 to change the Scope to remove something which is illegal or impossible |
Prompt the SM to create a follow up action - SM Compensation Event |
19.1 to submit a quotation for a Task |
Create a follow up action - Contractor Submission |
21.1 to submit particulars of design of an item of Equipment |
Create a follow up action - Contractor Submission |
32.2 to submit a revised plan |
Create a follow up action - Contractor Programme |
34.2 to submit a revised Task Order programme |
Create a follow up action - Contractor Programme |
36.1 to stop or not start work |
Prompt the SM to create a follow up action - SM Compensation Event |
X10.4(3) to submit a revised Information Execution Plan |
Create a follow up action - Contractor Submission |
Service Manager Notifications
Clause |
Action |
17.1 of an ambiguity or inconsistency |
Create a follow up action - Service Manager Instruction |
17.2 of an illegal or impossible requirement |
Create a follow up action - Contractor Early Warning |
Contractor Notifications
Clause |
Action |
17.1 of an ambiguity or inconsistency |
Create a follow up action - Service Manager Instruction |
17.2 of an illegal or impossible requirement |
Create a follow up action - Service Manager Instruction |
NEC4 TSS
Contractor Instructions
Clause |
Action |
14.3 to change the Scope, a Task or the Affected Property |
Prompt the Contractor to create a follow up action - Contractor Compensation Event |
17.2 to change the Scope to remove something which is illegal or impossible |
Prompt the Contractor to create a follow up action - Contractor Compensation Event |
21.1 to submit particulars of design of an item of Equipment |
Create a follow up action - Subcontractor Submission |
32.2 to submit a revised plan |
Create a follow up action - Subcontractor Submission |
34.2 to submit a revised Task Order programme |
Create a follow up action - Subcontractor Submission |
36.1 to stop or not start work |
Prompt the Contractor to create a follow up action - Contractor Compensation Event |
X10.4(3) to submit a revised Information Execution Plan |
Create a follow up action - Subcontractor Submission |
Contractor Notifications
Clause |
Action |
17.1 of an ambiguity or inconsistency |
Prompt the Contractor to create a follow up action - Contractor Instruction |
17.2 of an illegal or impossible requirement |
Prompt the Contractor to create a follow up action - Contractor Instruction |
Subcontractor Notifications
Clause |
Action |
17.1 of an ambiguity or inconsistency |
Prompt the Contractor to create a follow up action - Contractor Instruction |
17.2 of an illegal or impossible requirement |
Prompt the Contractor to create a follow up action - Contractor Instruction |
NEC4 TSSC
Client's Agent Instructions
Clause |
Action |
14.2 to change the Scope or a Task Order |
Prompt the Client's Agent to create a follow up action - Client's Agent Compensation Event |
30.2 to stop or not start work |
Prompt the Client's Agent to create a follow up action - Client's Agent Compensation Event |
30.2 to remove work from the Scope |
Prompt the Client's Agent to create a follow up action - Client's Agent Compensation Event |