This article is a guide to which clauses will trigger actions within FastDraft under different NEC3 contracts.
This guide contains the following:
Related Articles:
Introduction
It's now also possible to configure certain communications to create a follow-up action based on the clause/type. For example, it's now possible to configure that a Project Manager's instruction to submit a programme creates an action on the Contractor to submit a programme a configured number of days later or to configure a reminder to resubmit when a programme is not accepted. Drop-down options can either be configured to always generate a follow-up action or to present a pop-up asking the user whether they would like to create a follow-up action. In either case, the resultant action is referred to as auto-generated. Auto-generated actions have a link to both the user and the communication that created them and can be edited/updated manually.
The following lists show which clauses are configured, by default, to either prompt the user to create a follow up action, or configured to automatically create a follow up action.
NEC3 ECC
Project Manager Instructions
Clause |
Action |
14.3 to change the Works Information or a Key Date |
Prompt the PM to create a follow up action - PM Compensation Event |
18.1 to change the Works Information to remove something which is illegal or impossible |
Prompt the PM to create a follow up action - PM Compensation Event |
23.1 to submit particulars of design of an item of Equipment |
Create a follow up action - Contractor Submission |
26.4 to submit proposed contract data for a subcontract (main Options C, D, E and F) |
Create a follow up action - Contractor Submission |
32.2 to submit a revised programme |
Create a follow up action - Contractor Programme |
34.1 to stop or not start work |
Prompt the PM to create a follow up action - PM Compensation Event |
36.1 to submit a quotation for acceleration |
Create a follow up action - Contractor Submission with Quote |
73.1 on how to deal with an object of value of historical interest |
Prompt the PM to create a follow up action - PM Compensation Event |
Project Manager Notifications
Clause |
Action |
17.1 of an ambiguity or inconsistency |
Create a follow up action - PM Instruction |
Contractor Notifications
Clause |
Action |
17.1 of an ambiguity or inconsistency |
Create a follow up action - PM Instruction |
18.1 of an illegal or impossible requirement |
Create a follow up action - PM Instruction |
73.1 that an object of value of of historical or other interest has been found |
Create a follow up action - PM Instruction |
NEC3 ECS
Contractor Instructions
Clause |
Action |
14.3 to change the Subcontract Works Information or a Key Date |
Prompt the Contractor to create a follow up action - Contractor Compensation Event |
18.1 to change the Subcontract Works Information to remove something which is illegal or impossible |
Prompt the Contractor to create a follow up action - Contractor Compensation Event |
23.1 to submit particulars of design of an item of Equipment |
Create a follow up action - Subcontractor Submission |
26.4 to submit proposed contract data for a subsubcontract (main Options C, D, E and F) |
Create a follow up action - Subcontractor Submission |
32.2 to submit a revised programme |
Create a follow up action - Subcontractor Programme |
34.1 to stop or not start work |
Prompt the Contractor to create a follow up action - Contractor Compensation Event |
36.1 to submit a quotation for acceleration |
Create a follow up action - Subcontractor Submission with Quote |
73.1 on how to deal with an object of value of historical interest |
Prompt the Contractor to create a follow up action - Contractor Compensation Event |
Contractor Notifications
Clause |
Action |
17.1 of an ambiguity or inconsistency |
Create a follow up action - Contractor Instruction |
Subcontractor Notifications
Clause |
Action |
17.1 of an ambiguity or inconsistency |
Create a follow up action - Contractor Instruction |
18.1 of an illegal or impossible requirement |
Create a follow up action - Contractor Instruction |
NEC3 ECSC
Employer Instructions
Clause |
Action |
14.2 to change the Works Information |
Prompt the Employer to create a follow up action - Employer Compensation Event |
30.4 to stop or not start work |
Prompt the Employer to create a follow up action - Employer Compensation Event |
70.1 on how to deal with an object of value or historical interest |
Prompt the Employer to create a follow up action - Employer Compensation Event |
NEC3 ECSS
Contractor Instructions
Clause |
Action |
14.2 to change the Works Information |
Prompt the Contractor to create a follow up action - Contractor Compensation Event |
30.4 to stop or not start work |
Prompt the Contractor to create a follow up action - Contractor Compensation Event |
70.1 on how to deal with an object of value or historical interest |
Prompt the Contractor to create a follow up action - Contractor Compensation Event |
NEC3 FC
Service Manager Instructions
Clause |
Action |
14.3 to change the Service Information |
Prompt the Service Manager to create a follow up action - Service Manager Compensation Event |
22.1 to submit a revised programme |
Create a follow up action - Contractor Programme |
23.1 to submit particulars of the design of an item of Equipment |
Create a follow up action - Contractor Submission |
26.4 to submit proposed contract data for a Subcontractor (main Options C and E) |
Create a follow up action - Contractor Submission |
32.2 to stop or not start work |
Prompt the Service Manager to create a follow up action - Service Manager Compensation Event |
86.1 to submit insurance policies |
Create a follow up action - Contractor Submission |
Service Manager Notifications
Clause |
Action |
17.1 of an ambiguity or inconsistency |
Create a follow up action - Service Manager Instruction |
18.1 of an illegal or impossible requirement |
Create a follow up action - Service Manager Instruction |
Contractor Notifications
Clause |
Action |
17.1 of an ambiguity or inconsistency |
Create a follow up action - Service Manager Instruction |
NEC3 PSC
Employer Instructions
Clause |
Action |
17.1 to change the Scope to remove something which is illegal or impossible |
Prompt the Employer to create a follow up action - Employer Compensation Event |
20.2 to change the Scope or a Key Date |
Prompt the Employer to create a follow up action - Employer Compensation Event |
24.4 to submit proposed contract data for a subcontract (main Options C and E) |
Create a follow up action - Consultant Submission |
32.2 to submit a revised programme |
Create a follow up action - Consultant Programme |
33.1 to stop or not start work |
Prompt the Employer to create a follow up action - Employer Compensation Event |
34.1 to submit a quotation for acceleration |
Create a follow up action - Consultant Submission with Quote |
Employer Notifications
Clause |
Action |
16.1 of an ambiguity or inconsistency |
Create a follow up action - Employer Instruction |
Consultant Notifications
Clause |
Action |
16.1 of an ambiguity or inconsistency |
Create a follow up action - Employer Instruction |
17.1 of an illegal or impossible requirement |
Create a follow up action - Employer Instruction |
NEC3 PSSC
Client Instructions
Clause |
Action |
20.2 to change the Scope |
Prompt the Client to create a follow up action - Client Compensation Event |
30.3 to stop or not start work |
Prompt the Client to create a follow up action - Client Compensation Event |
NEC3 SC
Supply Manager Instructions
Clause |
Action |
14.3 to change the Goods Information |
Prompt the Supply Manager to create a follow up action - Supply Manager Compensation Event |
18.1 to change the Goods Information to remove something which is illegal or impossible |
Prompt the Supply Manager to create a follow up action - Supply Manager Compensation Event |
32.2 to submit a revised programme |
Create a follow up action - Supplier Programme |
34.1 to stop or not start work |
Prompt the Supply Manager to create a follow up action - Supply Manager Compensation Event |
35.1 to submit a quotation for acceleration |
Create a follow up action - Supplier Submission with Quote |
85.1 to submit insurance policy information for acceptance |
Create a follow up action - Supplier Submission |
Supply Manager Notifications
Clause |
Action |
17.1 of an ambiguity or inconsistency |
Create a follow up action - Supply Manager Instruction |
Supplier Notifications
Clause |
Action |
17.1 of an ambiguity or inconsistency |
Create a follow up action - Supply Manager Instruction |
NEC3 SSC
Purchaser Instructions
Clause |
Action |
14.1 to change the Goods Information |
Prompt the Purchaser to create a follow up action - Purchaser Compensation Event |
14.2 to change the Delivery Date |
Prompt the Purchaser to create a follow up action - Purchaser Compensation Event |
31.1 to stop or not start work |
Prompt the Purchaser to create a follow up action - Purchaser Compensation Event |
NEC3 TSC
Service Manager Instructions
Clause |
Action |
14.3 to change the Service Information |
Prompt the Service Manager to create a follow up action - Service Manager Compensation Event |
18.1 to change the Service Information to remove something which is illegal or impossible |
Prompt the Service Manager to create a follow up action - Service Manager Compensation Event |
22.1 to submit a revised programme |
Create a follow up action - Contractor Programme |
23.1 to submit particulars of the design of an item of Equipment |
Create a follow up action - Contractor Submission |
26.4 to submit proposed contract data for a Subcontractor (main Options C and E) |
Create a follow up action - Contractor Submission |
32.2 to stop or not start work |
Prompt the Service Manager to create a follow up action - Service Manager Compensation Event |
86.1 to submit insurance policies |
Create a follow up action - Contractor Submission |
Service Manager Notifications
Clause |
Action |
17.1 of an ambiguity or inconsistency |
Create a follow up action - Service Manager Instruction |
18.1 of an illegal or impossible requirement |
Create a follow up action - Service Manager Instruction |
Contractor Notifications
Clause |
Action |
17.1 of an ambiguity or inconsistency |
Create a follow up action - Service Manager Instruction |
NEC3 TSSC
Service Manager Instructions
Clause |
Action |
14.3 to change the Service Information |
Prompt the Service Manager to create a follow up action - Service Manager Compensation Event |
18.1 to change the Service Information to remove something which is illegal or impossible |
Prompt the Service Manager to create a follow up action - Service Manager Compensation Event |
22.1 to submit a revised programme |
Create a follow up action - Contractor Programme |
23.1 to submit particulars of the design of an item of Equipment |
Create a follow up action - Contractor Submission |
26.4 to submit proposed contract data for a Subcontractor (main Options C and E) |
Create a follow up action - Contractor Submission |
32.2 to stop or not start work |
Prompt the Service Manager to create a follow up action - Service Manager Compensation Event |
86.1 to submit insurance policies |
Create a follow up action - Contractor Submission |
Service Manager Notifications
Clause |
Action |
17.1 of an ambiguity or inconsistency |
Create a follow up action - Service Manager Instruction |
18.1 of an illegal or impossible requirement |
Create a follow up action - Service Manager Instruction |
Contractor Notifications
Clause |
Action |
17.1 of an ambiguity or inconsistency |
Create a follow up action - Service Manager Instruction |
Comments
0 comments