This article is a guide to which clauses will trigger actions within FastDraft under different NEC3 contracts.
This guide contains the following:
Related Articles:
Introduction
For those using the new Action Reminders and To Do List (i.e. the action sidebar shows a tick instead of a bell), it's now also possible to configure certain communications to create a follow-up action based on the clause/type. For example, it's now possible to configure that a Project Manager's instruction to submit a programme creates an action on the Contractor to submit a programme a configured number of days later or to configure a reminder to resubmit when a programme is not accepted. Drop-down options can either be configured to always generate a follow-up action or to present a pop-up asking the user whether they would like to create a follow-up action. In either case, the resultant action is referred to as auto-generated. Auto-generated actions have a link to both the user and the communication that created them and can be edited/updated manually.
Our latest NEC3 master templates (v4.0 and above) have been updated to take advantage of this new capability as outlined below.
NEC3 ECC
Project Manager Instructions
| Clause |
Action |
| 14.3 to change the Works Information or a Key Date |
Prompt the PM to create a follow up action - PM Compensation Event |
| 18.1 to change the Works Information to remove something which is illegal or impossible |
Prompt the PM to create a follow up action - PM Compensation Event |
| 23.1 to submit particulars of design of an item of Equipment |
Create a follow up action - Contractor Submission |
| 26.4 to submit proposed contract data for a subcontract (main Options C, D, E and F) |
Create a follow up action - Contractor Submission |
| 32.2 to submit a revised programme |
Create a follow up action - Contractor Programme |
| 34.1 to stop or not start work |
Prompt the PM to create a follow up action - PM Compensation Event |
| 36.1 to submit a quotation for acceleration |
Create a follow up action - Contractor Submission with Quote |
| 73.1 on how to deal with an object of value of historical interest |
Prompt the PM to create a follow up action - PM Compensation Event |
Project Manager Notifications
| Clause |
Action |
| 17.1 of an ambiguity or inconsistency |
Create a follow up action - PM Instruction |
Contractor Notifications
| Clause |
Action |
| 17.1 of an ambiguity or inconsistency |
Create a follow up action - PM Instruction |
| 18.1 of an illegal or impossible requirement |
Create a follow up action - PM Instruction |
| 73.1 that an object of value of of historical or other interest has been found |
Create a follow up action - PM Instruction |
NEC3 ECS
Contractor Instructions
| Clause |
Action |
| 14.3 to change the Subcontract Works Information or a Key Date |
Prompt the Contractor to create a follow up action - Contractor Compensation Event |
| 18.1 to change the Subcontract Works Information to remove something which is illegal or impossible |
Prompt the Contractor to create a follow up action - Contractor Compensation Event |
| 23.1 to submit particulars of design of an item of Equipment |
Create a follow up action - Subcontractor Submission |
| 26.4 to submit proposed contract data for a subsubcontract (main Options C, D, E and F) |
Create a follow up action - Subcontractor Submission |
| 32.2 to submit a revised programme |
Create a follow up action - Subcontractor Programme |
| 34.1 to stop or not start work |
Prompt the Contractor to create a follow up action - Contractor Compensation Event |
| 36.1 to submit a quotation for acceleration |
Create a follow up action - Subcontractor Submission with Quote |
| 73.1 on how to deal with an object of value of historical interest |
Prompt the Contractor to create a follow up action - Contractor Compensation Event |
Contractor Notifications
| Clause |
Action |
| 17.1 of an ambiguity or inconsistency |
Create a follow up action - Contractor Instruction |
Subcontractor Notifications
| Clause |
Action |
| 17.1 of an ambiguity or inconsistency |
Create a follow up action - Contractor Instruction |
| 18.1 of an illegal or impossible requirement |
Create a follow up action - Contractor Instruction |
NEC3 ECSC
Employer Instructions
| Clause |
Action |
| 14.2 to change the Works Information |
Prompt the Employer to create a follow up action - Employer Compensation Event |
| 30.4 to stop or not start work |
Prompt the Employer to create a follow up action - Employer Compensation Event |
| 70.1 on how to deal with an object of value or historical interest |
Prompt the Employer to create a follow up action - Employer Compensation Event |
NEC3 ECSS
Contractor Instructions
| Clause |
Action |
| 14.2 to change the Works Information |
Prompt the Contractor to create a follow up action - Contractor Compensation Event |
| 30.4 to stop or not start work |
Prompt the Contractor to create a follow up action - Contractor Compensation Event |
| 70.1 on how to deal with an object of value or historical interest |
Prompt the Contractor to create a follow up action - Contractor Compensation Event |
NEC3 FC
Service Manager Instructions
| Clause |
Action |
| 14.3 to change the Service Information |
Prompt the Service Manager to create a follow up action - Service Manager Compensation Event |
| 22.1 to submit a revised programme |
Create a follow up action - Contractor Programme |
| 23.1 to submit particulars of the design of an item of Equipment |
Create a follow up action - Contractor Submission |
| 26.4 to submit proposed contract data for a Subcontractor (main Options C and E) |
Create a follow up action - Contractor Submission |
| 32.2 to stop or not start work |
Prompt the Service Manager to create a follow up action - Service Manager Compensation Event |
| 86.1 to submit insurance policies |
Create a follow up action - Contractor Submission |
Service Manager Notifications
| Clause |
Action |
| 17.1 of an ambiguity or inconsistency |
Create a follow up action - Service Manager Instruction |
| 18.1 of an illegal or impossible requirement |
Create a follow up action - Service Manager Instruction |
Contractor Notifications
| Clause |
Action |
| 17.1 of an ambiguity or inconsistency |
Create a follow up action - Service Manager Instruction |
NEC3 PSC
Employer Instructions
| Clause |
Action |
| 17.1 to change the Scope to remove something which is illegal or impossible |
Prompt the Employer to create a follow up action - Employer Compensation Event |
| 20.2 to change the Scope or a Key Date |
Prompt the Employer to create a follow up action - Employer Compensation Event |
| 24.4 to submit proposed contract data for a subcontract (main Options C and E) |
Create a follow up action - Consultant Submission |
| 32.2 to submit a revised programme |
Create a follow up action - Consultant Programme |
| 33.1 to stop or not start work |
Prompt the Employer to create a follow up action - Employer Compensation Event |
| 34.1 to submit a quotation for acceleration |
Create a follow up action - Consultant Submission with Quote |
Employer Notifications
| Clause |
Action |
| 16.1 of an ambiguity or inconsistency |
Create a follow up action - Employer Instruction |
Consultant Notifications
| Clause |
Action |
| 16.1 of an ambiguity or inconsistency |
Create a follow up action - Employer Instruction |
| 17.1 of an illegal or impossible requirement |
Create a follow up action - Employer Instruction |
NEC3 PSSC
Client Instructions
| Clause |
Action |
| 20.2 to change the Scope |
Prompt the Client to create a follow up action - Client Compensation Event |
| 30.3 to stop or not start work |
Prompt the Client to create a follow up action - Client Compensation Event |
NEC3 SC
Supply Manager Instructions
| Clause |
Action |
| 14.3 to change the Goods Information |
Prompt the Supply Manager to create a follow up action - Supply Manager Compensation Event |
| 18.1 to change the Goods Information to remove something which is illegal or impossible |
Prompt the Supply Manager to create a follow up action - Supply Manager Compensation Event |
| 32.2 to submit a revised programme |
Create a follow up action - Supplier Programme |
| 34.1 to stop or not start work |
Prompt the Supply Manager to create a follow up action - Supply Manager Compensation Event |
| 35.1 to submit a quotation for acceleration |
Create a follow up action - Supplier Submission with Quote |
| 85.1 to submit insurance policy information for acceptance |
Create a follow up action - Supplier Submission |
Supply Manager Notifications
| Clause |
Action |
| 17.1 of an ambiguity or inconsistency |
Create a follow up action - Supply Manager Instruction |
Supplier Notifications
| Clause |
Action |
| 17.1 of an ambiguity or inconsistency |
Create a follow up action - Supply Manager Instruction |
NEC3 SSC
Purchaser Instructions
| Clause |
Action |
| 14.1 to change the Goods Information |
Prompt the Purchaser to create a follow up action - Purchaser Compensation Event |
| 14.2 to change the Delivery Date |
Prompt the Purchaser to create a follow up action - Purchaser Compensation Event |
| 31.1 to stop or not start work |
Prompt the Purchaser to create a follow up action - Purchaser Compensation Event |
NEC3 TSC
Service Manager Instructions
| Clause |
Action |
| 14.3 to change the Service Information |
Prompt the Service Manager to create a follow up action - Service Manager Compensation Event |
| 18.1 to change the Service Information to remove something which is illegal or impossible |
Prompt the Service Manager to create a follow up action - Service Manager Compensation Event |
| 22.1 to submit a revised programme |
Create a follow up action - Contractor Programme |
| 23.1 to submit particulars of the design of an item of Equipment |
Create a follow up action - Contractor Submission |
| 26.4 to submit proposed contract data for a Subcontractor (main Options C and E) |
Create a follow up action - Contractor Submission |
| 32.2 to stop or not start work |
Prompt the Service Manager to create a follow up action - Service Manager Compensation Event |
| 86.1 to submit insurance policies |
Create a follow up action - Contractor Submission |
Service Manager Notifications
| Clause |
Action |
| 17.1 of an ambiguity or inconsistency |
Create a follow up action - Service Manager Instruction |
| 18.1 of an illegal or impossible requirement |
Create a follow up action - Service Manager Instruction |
Contractor Notifications
| Clause |
Action |
| 17.1 of an ambiguity or inconsistency |
Create a follow up action - Service Manager Instruction |
NEC3 TSSC
Service Manager Instructions
| Clause |
Action |
| 14.3 to change the Service Information |
Prompt the Service Manager to create a follow up action - Service Manager Compensation Event |
| 18.1 to change the Service Information to remove something which is illegal or impossible |
Prompt the Service Manager to create a follow up action - Service Manager Compensation Event |
| 22.1 to submit a revised programme |
Create a follow up action - Contractor Programme |
| 23.1 to submit particulars of the design of an item of Equipment |
Create a follow up action - Contractor Submission |
| 26.4 to submit proposed contract data for a Subcontractor (main Options C and E) |
Create a follow up action - Contractor Submission |
| 32.2 to stop or not start work |
Prompt the Service Manager to create a follow up action - Service Manager Compensation Event |
| 86.1 to submit insurance policies |
Create a follow up action - Contractor Submission |
Service Manager Notifications
| Clause |
Action |
| 17.1 of an ambiguity or inconsistency |
Create a follow up action - Service Manager Instruction |
| 18.1 of an illegal or impossible requirement |
Create a follow up action - Service Manager Instruction |
Contractor Notifications
| Clause |
Action |
| 17.1 of an ambiguity or inconsistency |
Create a follow up action - Service Manager Instruction |